As of March 16th the second floor concrete has been poured. The first floor concrete is planned for March 29th. Our slab,mechanical,electrical and architural plans from Chainis and Anderson will be complete March 19th. I have also been working on our signage through Spectrum and things seem to be looking really good. The shell still looks the same so no new photos as of right now. Josh�